Successful Completion of Turnkey Ballast Water Treatment Project in Ferrol, Spain

We are delighted to announce the successful completion of an extensive turnkey project: Installation of a Ballast Water Treatment System (BWTS) in Ferrol, Spain. 

The project encompassed a range of pivotal stages, from conducting ship site surveys and feasibility studies to overseeing procurement, installation, and commissioning processes. Our professionals meticulously handled each step to ensure project success while fully complying with international regulations.  

 

Ship Site Survey and 3D Scan: The project commenced with a comprehensive ship site survey and a precise 3D scan of the vessel. This initial phase set the foundation for accurate project planning and system integration.

Feasibility Study and BWTS Selection: In close collaboration with maritime authorities and experts, an exhaustive feasibility study was conducted to identify the most suitable Ballast Water Treatment System for the vessel's unique specifications. The selection process adhered to stringent environmental standards while considering the ship's operational requirements.

Procurement and Installation: Once the BWTS was chosen, our team managed the procurement process meticulously. This involved sourcing quality components and ensuring timely delivery. The subsequent installation phase occurred in the shipyard, where the system was seamlessly integrated into the vessel's existing infrastructure.

 

Commissioning and Testing: The commissioning phase was pivotal in the project's timeline. Our dedicated engineers and technicians worked diligently to ensure that every aspect of the BWTS was functional and optimized for performance. Rigorous testing procedures were conducted to validate the system's efficiency and compliance with international regulations.

Ballast Water Management Plans (BWMP): Our experts collaborated with the ship's crew to develop comprehensive Ballast Water Management Plans in parallel with the system installation. These plans outline best practices for maintaining the system, managing ballast water, and ensuring ongoing compliance.

Class Approval and BWTS Sampling: To guarantee the BWTS's adherence to class society regulations, we obtained essential class approvals and certifications. Rigorous testing and sampling procedures were conducted to validate the system's effectiveness in treating ballast water and safeguarding marine ecosystems.

We extend our gratitude to the dedicated teams, partners, and stakeholders who contributed to the successful execution of this project. Their collective expertise, relentless dedication, and innovative spirit were instrumental in completing projects successfully. We are currently engaged in similar ongoing projects in China, Canada, the USA, Turkey, Australia, and India. For more information and similar solutions contact our team at This email address is being protected from spambots. You need JavaScript enabled to view it.

Albion Marine Solutions Ltd.

Suite 304 - 800 Carleton Court 

Delta, BC V3M 6Y6

Canada

Email : info@albionmarine.com

Tel     : +1 604 529 8488

Home

Our Services

Contact Us

News 

Careers